Miscalculations cost India’s moon mission
Filed under: Science & Technology; Tagged as: 100km, BARC, Chandrayaan, Chandrayaan-2, Chandrayaan-I, Chandrayan, Chandrayan-2, Chandrayan-I, first star, further studies, gravitational field, gyroscopes, india, isro, isro satellite, ISRO Satellite Centre, launch, Lunar Reconnaissance Orbiter, lunar surface, miscalculation, Moon, moon mission, orbit around the moon, payloads, perturbations, satellite centre, snags, space agency, star sensor, star sensors, tempor, thermal protection, thermal vacuum testNo Commentspopping..The reasons for early termination of the Chandrayaan-I mission are now tumbling out and they reveal that ISRO had kept the Moon orbiter’s problems tightly under wraps.Contrary to the space agency’s explanation that Chandrayaan’s orbit around the Moon had been raised from 100km to 200km in May this year for a better view of the Moon’s surface, it is now known that this was because of a miscalculation of the Moon’s temperature that had led to faulty thermal protection.
Admitting this, Dr T K Alex, director, ISRO Satellite Centre, Bangalore, said, “We assumed that the temperature at 100km above the Moon’s surface would be around 75 degrees Celsius. However, it was more than 75 degrees and problems started to surface. We had to raise the orbit to 200km.”
On May 19, however, ISRO said it had raised Chandrayaan’s orbit to “enable further studies on orbit perturbations, gravitational field variation of the Moon and also enable imaging of the lunar surface with a wider swath”.
It now transpires that heating problems on the craft had begun as early as November 25, 2008, forcing ISRO to deactivate some of the payloads – there were 11 in all.
As a result, some of the experiments could not be carried out which raised questions on whether the pre-launch thermal vacuum test done on the spacecraft at the ISRO Satellite Centre in Bangalore was adequate.
In early 2009, the situation improved and Chandrayaan-1 started operating normally. However, the snags resurfaced. This time with the two star sensors of Chandrayaan because of high temperature. The sensors are crucial in determining the orientation of the craft in space.
The first star sensor packed up on April 26, and even the back-up sensor failed during the second week of May.
ISRO officials said scientists and engineers used ingenious ways to restore Chandrayaan-I by using gyroscopes. An official requesting anonymity acknowledged: “This was purely a temporary step. It was like a broken car’s steering wheel being repaired with scotch tapes. We could not predict how long this arrangement would last,” he admitted.
The official said much before the official announcement of the project’s end on August 30, it had become clear that the two-year mission would be cut short since 95% of the scientific goals had been accomplished.
Despite the failure of the star sensors, Chandrayaan-1 transmitted excellent images including that of the solar eclipse on July 22. Also at 12.30am on August 21, it flew along with Nasa’s Lunar Reconnaissance Orbiter (LRO) for four minutes to detect water ice in the north pole of the moon.
But worse was to follow. At 1.30am on August 29, communication with the spacecraft snapped all of a sudden. ISRO chairman Madhavan Nair has been quoted as saying that due to unforeseen radiation problems the two computers in the spacecraft controlling communication got affected resulting in the breakdown of communications. He has admitted that many of the heat-related problems were not anticipated at all, and it was definitely a learning experience.
“Keeping this in mind, Chandrayaan-2’s thermal design will be strengthened to withstand more than 100 degrees Celsius,” Alex told on the sidelines of the recently concluded eighth international conference on low cost planetary mission conducted by the International Academy of Astronautics in Goa.
BARC is collaborating with ISRO to strengthen the radiation shield of Chandrayaan-2, slated for lift off in 2013 from Sriharikota. The average day temperature on the Moon’s surface is 107 degrees Celsius, while the mean night temperature is -153 degree Celsius.
Although, ISRO claims that 95% of its planned experiments have been completed, it remains to be known whether payloads designed to operate at a 100-km orbit completed their missions. The issue has triggered a fierce debate on whether ISRO should have declared it a one-year mission right at the beginning rather than an ambitious two-year programme.
Among the experiments to be conducted from a 100km orbit were observations in the visible, near-infrared and soft and hard X-rays. Further, the Lunar Laser Ranging Instrument’s objective was to provide ranging data for determining the height difference between the spacecraft and the lunar surface. Scientists admit that at an altitude of 200km, the return signal could be too weak for the purpose.
Chandrayaan’s objectives also included orbiting around the Moon at a height of 100km for chemical, mineralogical and photo-geologic mapping of the surface and its X-ray spectrometer was to use X-rays to map the surface composition of the Moon and help scientists understand its origin and evolution, as well as quantifying the mineral resources that exist there.
The spacecraft’s 11 scientific instruments were built in India, USA, UK, Germany, Sweden and Bulgaria. The mission was formally called off on August 30 by ISRO, which said that a failure analysis committee will probe into the matter. ISRO chairperson G Madhavan Nair also said US and European space agencies who had also taken part in the Indian space mission “were satisfied” with the results.
The reasons for early termination of the Chandrayaan-I mission are now tumbling out and they reveal that ISRO had kept the Moon orbiter’s problems tightly under wraps.Contrary to the space agency’s explanation that Chandrayaan’s orbit around the Moon had been raised from 100km to 200km in May this year for a better view of the Moon’s surface, it is now known that this was because of a miscalculation of the Moon’s temperature that had led to faulty thermal protection.
Admitting this, Dr T K Alex, director, ISRO Satellite Centre, Bangalore, said, “We assumed that the temperature at 100km above the Moon’s surface would be around 75 degrees Celsius. However, it was more than 75 degrees and problems started to surface. We had to raise the orbit to 200km.”
On May 19, however, ISRO said it had raised Chandrayaan’s orbit to “enable further studies on orbit perturbations, gravitational field variation of the Moon and also enable imaging of the lunar surface with a wider swath”.
It now transpires that heating problems on the craft had begun as early as November 25, 2008, forcing ISRO to deactivate some of the payloads – there were 11 in all.
As a result, some of the experiments could not be carried out which raised questions on whether the pre-launch thermal vacuum test done on the spacecraft at the ISRO Satellite Centre in Bangalore was adequate.
In early 2009, the situation improved and Chandrayaan-1 started operating normally. However, the snags resurfaced. This time with the two star sensors of Chandrayaan because of high temperature. The sensors are crucial in determining the orientation of the craft in space.
The first star sensor packed up on April 26, and even the back-up sensor failed during the second week of May.
ISRO officials said scientists and engineers used ingenious ways to restore Chandrayaan-I by using gyroscopes. An official requesting anonymity acknowledged: “This was purely a temporary step. It was like a broken car’s steering wheel being repaired with scotch tapes. We could not predict how long this arrangement would last,” he admitted.
The official said much before the official announcement of the project’s end on August 30, it had become clear that the two-year mission would be cut short since 95% of the scientific goals had been accomplished.
Despite the failure of the star sensors, Chandrayaan-1 transmitted excellent images including that of the solar eclipse on July 22. Also at 12.30am on August 21, it flew along with Nasa’s Lunar Reconnaissance Orbiter (LRO) for four minutes to detect water ice in the north pole of the moon.
But worse was to follow. At 1.30am on August 29, communication with the spacecraft snapped all of a sudden. ISRO chairman Madhavan Nair has been quoted as saying that due to unforeseen radiation problems the two computers in the spacecraft controlling communication got affected resulting in the breakdown of communications. He has admitted that many of the heat-related problems were not anticipated at all, and it was definitely a learning experience.
“Keeping this in mind, Chandrayaan-2’s thermal design will be strengthened to withstand more than 100 degrees Celsius,” Alex told on the sidelines of the recently concluded eighth international conference on low cost planetary mission conducted by the International Academy of Astronautics in Goa.
BARC is collaborating with ISRO to strengthen the radiation shield of Chandrayaan-2, slated for lift off in 2013 from Sriharikota. The average day temperature on the Moon’s surface is 107 degrees Celsius, while the mean night temperature is -153 degree Celsius.
Although, ISRO claims that 95% of its planned experiments have been completed, it remains to be known whether payloads designed to operate at a 100-km orbit completed their missions. The issue has triggered a fierce debate on whether ISRO should have declared it a one-year mission right at the beginning rather than an ambitious two-year programme.
Among the experiments to be conducted from a 100km orbit were observations in the visible, near-infrared and soft and hard X-rays. Further, the Lunar Laser Ranging Instrument’s objective was to provide ranging data for determining the height difference between the spacecraft and the lunar surface. Scientists admit that at an altitude of 200km, the return signal could be too weak for the purpose.
Chandrayaan’s objectives also included orbiting around the Moon at a height of 100km for chemical, mineralogical and photo-geologic mapping of the surface and its X-ray spectrometer was to use X-rays to map the surface composition of the Moon and help scientists understand its origin and evolution, as well as quantifying the mineral resources that exist there.
The spacecraft’s 11 scientific instruments were built in India, USA, UK, Germany, Sweden and Bulgaria. The mission was formally called off on August 30 by ISRO, which said that a failure analysis committee will probe into the matter. ISRO chairperson G Madhavan Nair also said US and European space agencies who had also taken part in the Indian space mission “were satisfied” with the results.

Say bye bye to duplicate content.
Now, with WordPress Uniquefier v3.4 all your articles are 100% unique
What is Uniquefier and how is it going to help you?
Uniquefier is a WordPress Plugin which once activated will turn your blog content from duplicate to unique. All it takes is 1 single click to activate the plugin and everything will be 100% unique content.
You may be wondering how is this possible? Well, it is indeed, and no it’s not one of those article rewriters or any spinners you may have heard of. More, the articles will be the same for your site visitors, the changes which are being made to the articles are in the backpage, in the page source, changes which are not visible to the visitors, but only to the search engines bots and browsers. We are not adding hiding text or any kind of such activities which are strictly forbidden, the Uniquefier uses a simple, yet highly effective mechanism of turning your articles unique. It is a well known fact that search engines (for google has been proofed) can run and index non advanced JavaScript from your pages. This is why, by using a special technique we place the original articles under a JavaScript run. This way:- you get original content as the way you show the articles is different than just a pure copy+paste
- search engines understand what an untrained human eye can’t

Click here to view more detailsTags: 100km, BARC, Chandrayaan, Chandrayaan-2, Chandrayaan-I, Chandrayan, Chandrayan-2, Chandrayan-I, first star, further studies, gravitational field, gyroscopes, india, isro, isro satellite, ISRO Satellite Centre, launch, Lunar Reconnaissance Orbiter, lunar surface, miscalculation, Moon, moon mission, orbit around the moon, payloads, perturbations, satellite centre, snags, space agency, star sensor, star sensors, tempor, thermal protection, thermal vacuum test
Related posts:
Leave a Reply
Freelance Jobs At Scriptlance
- Website Crawler And Software IdentifierI need a solution that will crawl the web identifying sites that use the open source software Joomla, Wordpress, Drupal, Mambo, Alfresco, and Plone. I would want it to create line in a mysql database with: -the url of the site, -what software it's using, -what version of the software -the title tag -the description meta tag -the keywords meta tag We would want to point the program at a directory (like dmoz.org) to start. Then, have it find more URLs as it goes. So, the solution needs to fi…
- Joomla ChangesWe have a Joomla 1.5.18 installation with a customized theme and commercial and open source components, modules and plugins installed. We are experiencing two problems that we are looking to have resolved. 1. We have a drop down menu (praisemenu2 from PixelPraise) that on Internet Explorer will disappear behind the graphics when it drops down. The problem is intermittent and some Internet Explorer users are fine, while other experience it consistently. We believe it is a CSS problem with…
- New Advanced Penny Auction Looking for a team to create a new PennyAuction site. This site will be based on the Quibids model with the ability to add new features as we grow. We are looking to have this done in .net not PHP. Access to our servers will be granted to create/test the site. Also we have our own in house programer and graphics persons to help with the site layout and design. We would like to launch the basic version of this site asap. And then add more feature on a monthly basis. Please contact me…
- Joomla Database IntegrationWe need a joomla integration with ezlink POS system. This would include synching the user database, etc. Ezlink has provided their API information. I will provide the API information for your review in the PMB.
- Build Wordpress Site Using Google Base DataI am looking to build some wordpress sites using the data from a goole base feed. my site is www.executivegreetingcards.com and I have several other url's that I do not use right now. I want to use the thesis theme for wordpress and have the site formatted so that I can import the google base feed and it will build my product pages. Google base feed is here. http://www.executivegreetingcards.com/feed/feed.cfm I would like to change the url structure to each of the new domain names and c…
Partner links
Breaking News
- Maoists set another deadline, families cry for helpTime is running out for the 3 cops abducted by Maoist terrorists as the second deadline set for 10am looms near. After claiming to have killed Sub Inspector Abhay Yadav, the Maoists have set a new deadline of 10 am for the cops to release their leaders. If the Bihar govt refuses to give in, the Maoists have warned that they would kill the remaining policemen in custody.…
- Cops' distraught families plead for government helpThe families of the abducted cops have made a desperate plea to the government for the safe return of their loved ones. Even as Maoists claimed that they had killed sub inspector Abhay Yadav, the family members of the 3 remaining abducted cops have pleaded with Nitish Kumar to ensure the safe return of the policemen. The families of the three policemen have threatened to immolate themselves if their husbands dont return home safely.…
Twitter links powered by Tweet This v1.6.1, a WordPress plugin for Twitter.